Buying a Delray Condo Under Florida’s Condo Safety Laws: Milestone Inspections and SIRS

A generic well-maintained mid-rise South Florida condominium with empty balconies, tropical landscaping, and a quiet courtyard drive. No construction or notices.

By Kurt Lehmann, Lehmann Realty Inc

Florida law requires milestone structural inspections and Structural Integrity Reserve Studies for many residential condominium and cooperative buildings. The rules are about life safety and reserve funding, not about a building’s marketing label. They do not apply to every Delray-address condominium. Coverage turns on habitable stories, the certificate of occupancy, and whether the building is a residential condominium or cooperative. Garden-style buildings under three habitable stories may be outside the statutes even if they are condominiums.[1][2]

This is general information, not legal, engineering, or lending advice. Milestone-inspection and Structural Integrity Reserve Study requirements are set by Florida law and administered by the local building official and the association. A buyer should obtain the inspector-prepared milestone summary, the association’s most recent SIRS (or the statutory statement that the association is not required to have one), the budget and financials, and any special-assessment or loan information, and should confirm jurisdiction — city or unincorporated county — from the parcel’s control number. Confirm those documents before relying on a listing remark.

Current inventory of lower-priced Delray-area condominiums, villas, and townhomes is on the live Condos Under $400K page. This article is about the legal framework, not a listing guide, and it does not publish listing counts.[3]

Milestone inspections

Section 553.899, Florida Statutes, requires a milestone inspection of a residential condominium or cooperative building that is three habitable stories or more in height, as determined by the Florida Building Code. The word “habitable” was added by HB 913 (2025). The inspection is a structural inspection of load-bearing elements and the primary structural members and systems, by a Florida-licensed architect or engineer, to attest to the life safety and adequacy of the structural components. It is not a Florida Building Code or firesafety-code compliance inspection. The statute does not apply to a single-family, two-family, three-family, or four-family dwelling with three or fewer habitable stories above ground.[1]

The first inspection is due by December 31 of the year the building reaches 30 years of age, based on the certificate of occupancy, and every 10 years thereafter. If the certificate-of-occupancy date is unavailable, the local building official’s occupancy record is used. A building that reached 30 years of age before July 1, 2022 had to complete its initial inspection before December 31, 2024. A building that reached 30 years of age on or after July 1, 2022 and before December 31, 2024 had until December 31, 2025.[1]

The local enforcement agency may require the first inspection by December 31 of the year the building turns 25, based on local circumstances, including proximity to salt water, and then every 10 years. That is local discretion under the statute, not an automatic statewide 3-mile rule. (A 2022 “within 3 miles of a coastline” mandate was removed in 2023.) The City of Delray Beach and Palm Beach County still describe a 25-year trigger for buildings within 3 miles of the coast, and a 30-year trigger farther inland, on their milestone pages. Those are the city and county schedules, under the statute’s local-discretion provision. Confirm the schedule that applies to the building.[1][4]

The local agency must give written notice by certified mail, and the association must notify unit owners within 14 days. Phase one is a visual examination, to be completed within 180 days of the notice. Phase two is required if phase one finds “substantial structural deterioration” — substantial structural distress or weakness that negatively affects the building’s general structural condition and integrity. Surface imperfections alone do not qualify unless the inspector determines they are a sign of substantial structural deterioration. A phase-two progress report is due within 180 days after the phase-one report. After a phase-two report, counties and cities must adopt an ordinance setting a timeframe for repairs, and repairs must be commenced within 365 days after the report is received. The City of Delray Beach’s milestone page (accessed November 12, 2026) has said 180 days from the report to complete repairs unless the Building Official allows otherwise, extendable to a total of 365 days. That is a city-page description, not a substitute for the statute. The association must provide the inspector-prepared summary to unit owners within 45 days of receiving the report.[1][4]

The local agency may extend the initial deadline for good cause if the owner has contracted with an architect or engineer and the inspection cannot reasonably be completed by the deadline. A pre-July 1, 2022 structural inspection report may be accepted if it substantially complies; unit-owner notice requirements still apply.[1]

Who the building official is depends on the parcel. Inside city limits, the City of Delray Beach Building Division is the local enforcement agency (filings through the city’s eServices portal). Unincorporated parcels with a Delray Beach mailing address fall under Palm Beach County Planning, Zoning and Building, at 561-233-5020. The first two digits of the parcel control number are 12 for the City of Delray Beach and 00 for unincorporated Palm Beach County. Many large west-of-I-95 condo communities — for example Kings Point, Huntington Lakes, and Villages of Oriole — are unincorporated (prefix 00) even when the mailing city is Delray Beach. Those names are jurisdiction examples only; this article does not state a compliance status for any building. Confirm the PCN and the office that holds the filing.[5]

Structural Integrity Reserve Study

A Structural Integrity Reserve Study, under s. 718.112(2)(g), is a budget-planning study of the structural and safety-related components the association is required to maintain, the existing reserve fund, and the funding needed for future major repair and replacement. A residential condominium association must have a SIRS completed at least every 10 years for each building on the condominium property that is three habitable stories or higher. The study is based on a visual inspection and must be performed or verified by a Florida-licensed engineer or architect, or a person certified as a reserve specialist or professional reserve analyst by CAI or APRA.[2]

Required components are: roof; structure, including load-bearing walls and primary structural members and systems; fireproofing and fire protection systems; plumbing; electrical systems; waterproofing and exterior painting; windows and exterior doors; and any other item with a deferred-maintenance expense or replacement cost over $25,000 (or the division’s inflation-adjusted amount) whose failure would negatively affect those items, as determined by the visual inspection. DBPR points to its Reserve Threshold page for the annually adjusted dollar figure. Confirm the current threshold.[2]

Associations existing on or before July 1, 2022 that are controlled by unit owners other than the developer must have a SIRS completed by December 31, 2025 for each such building. That date was extended from the original December 31, 2024 deadline by HB 913 (2025). An association that is required to complete a milestone inspection on or before December 31, 2026 may complete the SIRS simultaneously with that inspection, but “in no event may the structural integrity reserve study be completed after December 31, 2026.” As of November 20, 2026, the general December 31, 2025 deadline has passed; the December 31, 2026 outer limit remains for associations using the simultaneous-inspection provision. No later general statewide extension was found. Do not treat a later deadline as if one had been enacted.[2][6]

For a budget adopted on or after December 31, 2024, members of a unit-owner-controlled association that must obtain a SIRS may not waive SIRS reserves or provide less than the required amount, except a division-approved alternative funding method for a multicondominium, or if the condominium is being terminated under s. 718.117. Those reserves also may not be used for other purposes. Funding may be by regular assessments, special assessments, lines of credit, or loans, with a majority vote of the total voting interests for a special assessment, line of credit, or loan. Such financing must appear in the annual financial statement delivered to owners and provided to prospective purchasers under s. 718.503. A limited pause or reduction of reserve contributions for up to two consecutive budgets adopted on or before December 31, 2028, after a recent milestone inspection, is a separate statutory provision; it is not a waiver of the underlying SIRS duty. A milestone inspection within the past five years can replace only the visual-inspection portion of the SIRS. After a milestone inspection, the association may delay the SIRS for up to two consecutive budget years to focus on repairs. Willful and knowing failure to complete the study is a breach of fiduciary duty. Within 45 days after receiving the study, the association must distribute a copy to each unit owner or deliver a notice that it is available for inspection and copying on written request.[2]

After July 1, 2024, a completed SIRS must be reported to the division. DBPR maintains a public SIRS Reporting Database of complete, self-reported filings, in two lists: submissions before July 2025, and July 2025 and after. Absence from the list is not proof that a study was not done. Presence is not proof that reserves are funded or that repairs are complete. No public statewide building-by-building milestone database was found on DBPR’s Inspections page. This article does not publish a Delray compliance percentage, and it does not publish a “no SIRS” finding for any named building. Confirm status from the association’s documents and, for filings, from DBPR’s database and the local building official.[7]

What a buyer is entitled to see, and the cancellation windows

For contracts entered into after December 31, 2024, s. 718.503 requires conspicuous contract language about the inspector-prepared summary of the milestone inspection report, a turnover inspection report in the circumstances the statute describes, and the association’s most recent SIRS — or a conspicuous statement that the association is not required to have a milestone inspection or a SIRS, as applicable.[8]

On a nondeveloper resale, s. 718.503(2) requires statutory clauses in the contract. For the governing documents, the buyer may cancel by written notice within 7 days, excluding Saturdays, Sundays, and legal holidays, after signing and after receiving a current copy of the declaration, articles of incorporation, bylaws and rules, the most recent annual financial statement and annual budget, and the Frequently Asked Questions and Answers document, if requested in writing, unless the contract instead contains the buyer’s acknowledgment of receiving those documents more than 7 such days before signing. For contracts entered into after December 31, 2024, a separate clause applies the same 7-day window to the inspector-prepared milestone inspection summary, any required turnover inspection report, and the association’s most recent SIRS, if applicable. The buyer may extend closing by not more than those same 7 days after receiving the documents. A purported waiver of these rights has no effect, and the right terminates at closing. The older “three-day” resale figure is not the current statutory text.[8]

Developer sales use a 15-day cancellation structure, including a 15-day window, excluding Saturdays, Sundays, and legal holidays, tied to the milestone summary and SIRS, with a matching closing-extension right.[8]

The documents themselves show whether a milestone remained phase one or went to phase two, whether a SIRS has been completed, and whether a special assessment, line of credit, or loan appears on the financial statement. Special assessments, loans, and lines of credit used to fund SIRS or milestone work must be included in the annual financial statement delivered to unit owners and provided to prospective purchasers. This article does not invent a typical per-unit assessment for Delray. Confirm the figures in the association’s statement.[2][8]

A buyer’s lender will review the association’s documents, inspection status, reserves, and any special assessments as part of project review. Financing can be delayed or declined if the lender’s guidelines are not met. This article does not state a Fannie Mae or Freddie Mac rule that a missing milestone inspection or missing SIRS makes a building “non-warrantable.” That characterization was not verified from a primary GSE source. Confirm the lender’s project-review requirements.[9]

Quick questions

Does every Delray condo need a milestone inspection? No. The statute applies to residential condominium or cooperative buildings of three habitable stories or more, with a stated exception for one- to four-family dwellings with three or fewer habitable stories above ground. Low-rise garden buildings may be outside the statute.[1]

When is a milestone due? By December 31 of the year the building reaches 30 years of age, then every 10 years. The City of Delray Beach and Palm Beach County describe a 25-year first inspection for buildings within 3 miles of the coast. That is local practice under a discretionary statute, not a current statewide 3-mile mandate. Confirm the local schedule.[1][4]

What is a SIRS, and what is the deadline? It is the statutory reserve study of listed structural and safety components, at least every 10 years. Covered pre-July 1, 2022 owner-controlled associations had a general deadline of December 31, 2025. If completed with a milestone inspection due on or before December 31, 2026, the study still may not be completed after December 31, 2026.[2]

Can the association waive SIRS reserves? Not for budgets adopted on or after December 31, 2024, except narrow statutory exceptions (a division-approved multicondominium alternative, or termination).[2]

What documents does a buyer receive, and how long is the cancellation period? The inspector-prepared milestone summary and the most recent SIRS, or a statement that they are not required. On a resale, 7 days excluding Saturdays, Sundays, and legal holidays. On a developer contract, 15 days, with a 15-day weekend-and-holiday-excluded window for those documents.[8]

How can a SIRS filing be checked? DBPR’s SIRS Reporting Database shows complete, self-reported filings only. Also obtain the association documents. Absence from the database is not proof that no study was done.[7]

Will a missing inspection stop financing? That depends on the lender’s project review. This article does not state a Fannie Mae or Freddie Mac ineligibility test as fact.[9]

This is general information, not legal, engineering, or lending advice. Milestone-inspection and Structural Integrity Reserve Study requirements are set by Florida law and administered by the local building official and the association. Confirm the inspector-prepared milestone summary, the most recent SIRS or the statutory statement that one is not required, the financials, and the jurisdiction of the property from the parcel control number. For a tax question, talk with a qualified tax professional.

Get Lehmann Terms, our free Delray Beach real estate newsletter. Subscribe here.

— K

Kurt Lehmann, Florida Real Estate Broker, BK3176578 / Lehmann Realty Inc, Florida real estate brokerage, CQ1039474 / 111 SE 2nd Street, Suite 102, Delray Beach, FL 33444 / LehmannFlorida.com / Equal Housing Opportunity.

Sources

  1. s. 553.899, F.S. (2026), https://www.flsenate.gov/Laws/Statutes/2026/553.899 (rechecked November 20, 2026). DBPR, Inspections, https://condos.myfloridalicense.com/inspections/ (accessed November 20, 2026).
  2. s. 718.112, F.S. (2026), including (2)(f) and (2)(g), https://www.flsenate.gov/Laws/Statutes/2026/718.112 (rechecked November 20, 2026). DBPR, SIRS Reporting, https://www2.myfloridalicense.com/condos-timeshares-mobile-homes/condominiums-and-cooperatives-sirs-reporting/ (accessed November 20, 2026).
  3. Lehmann Florida, Condos Under $400K, https://lehmannflorida.com/delray-beach-condo-villa-townhomes-under-400k/ (live-page URL as recorded November 20, 2026).
  4. City of Delray Beach, Milestone Recertification, https://www.delraybeachfl.gov/government/city-departments/development-services/milestone-recertification; Palm Beach County PZB, Mandatory Milestone Inspections, https://discover.pbc.gov/pzb/building/Pages/Mandatory-Milestone-Inspections.aspx (accessed November 12, 2026).
  5. Palm Beach County Property Appraiser municipal list, https://pbcpao.gov/muni-list.htm (accessed November 20, 2026).
  6. HB 913 (2025) Senate bill summary, https://flsenate.gov/Committees/BillSummaries/2025/html/913; ch. 2026-14 (SB 104), reviser’s bill, https://laws.flrules.org/2026/14 (accessed November 12, 2026).
  7. DBPR SIRS Reporting Database, https://www2.myfloridalicense.com/condos-timeshares-mobile-homes/condominiums-and-cooperatives-sirs-reporting/; DBPR Inspections, https://condos.myfloridalicense.com/inspections/ (accessed November 20, 2026). OPPAGA Report 26-04 (July 2026), https://oppaga.fl.gov/Documents/Reports/26-04.pdf.
  8. s. 718.503, F.S. (2026), https://www.flsenate.gov/Laws/Statutes/2026/718.503 (rechecked November 20, 2026).
  9. No Fannie Mae or Freddie Mac rule on this point is stated in this article.

Check out this article next

Is Delray Beach in a Flood Zone? How to Read FEMA Maps East of I-95

Is Delray Beach in a Flood Zone? How to Read FEMA Maps East of I-95

Delray Beach is not in a single flood zone. Flood hazard is mapped parcel by parcel on FEMA Flood Insurance Rate Maps that became effective…

Read Article
About the Author